CASTRIES, St. Lucia, Aug 31, CMC – Opposition Leader Allen Chastanet, Tuesday said he “notes with interest” the decision by the St. Lucia government to a seven member committee to review the Hewanorra International Airport (HIA) Redevelopment Project, which the new administration said “has been shrouded by controversy”.
The HIA project is a US$175 million investment to re-develop the island’s international airport, south of here, “into an unmatched operation with significant enhancements to present facilities and major improvements to customer experience,” according to the HIA website.
In a statement, Chastanet said that it is “disappointing” that the St. Lucia Labour Party (SLP) government “continues to promote what we now know was the “Big Lie”.
“Firstly the US government never has investigated any minister as is relates to the HIA project, but we do know which minister they have investigated and continue to categorize him as a person of interest. A fact that the SLP have themselves highlighted, but chose to ignore when they included him in the current Cabinet,” he said.
In a statement, announcing a review of the project, the Office of the new Prime Minister, Phillip J. Pierre said that the committee, headed by Allison Jean, a former senior public servant “has been tasked to review the scope and financing arrangements of the HIA Redevelopment Project and to report its findings within 90 days”.
The statement said that the project “has been shrouded by controversy after court documents from the United States were filed and became public, naming ministers of the 2006-2011 United Workers Party (UWP) administration as persons of interest”.
Chastanet said that it is also interesting to note that Jean is heading the committee when she was previously the deputy chairperson of St. Lucia Air and Seaport Authority (SLASPA) between 2007-2011.
He said that it “was the same board who selected and recommended the consortium headed by A&M to the then Minister of Finance and the former Minister of Ports under the United Workers Party (UWP) government and the current Minister of Ports,” adding “both of whom have publicly supported the current financing mechanism.”
It the statement, the government said that in 2011, the then SLP government, through the IFC-World Bank negotiated a Public-Private Partnership (PPP), through a trusted global process for bidding and construction.
But it said that the arrangement was abandoned in 2016 by the Chastanet government resulting in the government of St. Lucia being fined one million US dollars.
“The UWP Administration opted to continue the redevelopment project through loan financing. Loans amounting to over EC$600 million (One EC dollar=US$0.37 cents) were accrued from a consortium of local banks and the Exim Bank of Taiwan,” the statement from the Office of the Prime Minister added.
But Chastanet said that the new government in its “continued attempt to attribute impropriety, must themselves be more transparent.
“More importantly, the SLP must stop the charade with regard to the financing of HIA. If they understood and genuinely cared about the viability of this project they would never have stopped the collection of the head tax in 2012 which we now know cost the citizens of St Lucia over EC$150 million.”
Chastanet said that under the current mechanism the head tax is US$35 per person and it would take 15 years to repay the loan which was approved by Taiwan. The proposed mechanism that the SLP wanted was a head tax of $55-60 for 30 years and it would include a concession to a private company.”
He said that under the current mechanism, SLASPA is the executing agency and the loan from Taiwan is for 20 years with a five year moratorium at an interest rate of no more than four per cent and that a second loan from a regional consortium of banks under the same terms and a third loan from the World Bank for 40 years at five per cent interest and a ten year moratorium.
“This in comparison to a 30 year concession at six per cent interest under the proposed PPP.”
The new government has said that it the review committee is expected to advise the Cabinet on the way forward as it relates to the loan financing or a return to the PPP agreement, pledging its commitment to the improvement and modernisation of the HIA.
CMC/es/ir/2021