PORT OF SPAIN, Trinidad, Sept 29, CMC – The Court of Appeal Friday dismissed an application by the Chinese contractor firm, China Jiangsu International Corporation (TT) for a variation of a court order that it pay TT$30.1 million (One TT dollar=US$0.16 cents) to the state-owned Housing Development Corporation (HDC).
The payment is due for wasted expenditure on two blocks at the Las Alturas Housing project in Morvant on the outskirts of the capital.
An 18-month public inquiry set up to investigate the process which led to the construction of the towers at Lady Young Gardens, Morvant, and all other acts, was laid in Parliament in September 2016.
The two multi-storey units began falling apart after construction, and the TT$26 million towers were earmarked for demolition. They were part of a larger project, which was originally budgeted at TT$67 million but later rose to TT$90 million.
The three-member Court of Appeal dismissed China Jiangsu’s application for a lack of cogent evidence that it ran the risk of financial ruin if forced to pay the judgment debt in full.
In April, the High Court ordered the contractor to compensate the HDC specific sums related to the two apartment blocks, which suffered structural damage and had to be demolished.
China Jiangsu has appealed the ruling and orders and in July, sought a stay of the order and a variation. While a conditional stay was granted, the contractor had to make a TT$15 million payment by August 15.
However, a temporary suspension of the stay was then granted in August, giving the company until September 28 to make the TT$15 million payment. But the Chinese contractor, unable to pay, sought the court’s intervention.
But in its ruling, the Appeal Court said the contractor’s application was not supported by cogent evidence to justify the court’s “holding its hand against the successful litigant benefitting from a judgment in its favour”.
In its application, China Jiangu, said it, too, was owed for work done and was expecting payment in order to satisfy the debt.
One of the company’s attorney, Keith Scotland, had suggested a staggering of the payment and in default the imposition of a sanction, assuring the court “we will be able to pay if given time.”
But Senior Counsel, Russell Martineau, who is heading the HDC team of lawyers, objected describing the situation as “scandalous.
“We (the HDC) are being treated as if we have no rights…The country needs the money. We have houses to build.”
CMC/af/ir/2023
